Name factors pertinent to site layout. Select “A” if the factor is pertinent to site layout and “B” if it is not.
Accessibility to major highways
Name factors pertinent to site layout. Select “A” if the factor is pertinent to site layout and “B” if it is not.
Local regulations and covenants (zoning and restrictions)
Name factors pertinent to site layout. Select “A” if the factor is pertinent to site layout and “B” if it is not.
Location of utilities
Name factors pertinent to site layout. Select “A” if the factor is pertinent to site layout and “B” if it is not.
Presence of existing trees and shrubs
Name factors pertinent to site layout. Select “A” if the factor is pertinent to site layout and “B” if it is not.
Contour or shape of site
Name factors pertinent to site layout. Select “A” if the factor is pertinent to site layout and “B” if it is not.
Height of proposed structure
Name factors pertinent to site layout. Select “A” if the factor is pertinent to site layout and “B” if it is not.
Characteristics of soil
Information used to lay out building lines. Select “A” if the information is used to lay out building lines and “B” if it is not.
Setback from property lines
Information used to lay out building lines. Select “A” if the information is used to lay out building lines and “B” if it is not.
Direction building faces
Information used to lay out building lines. Select “A” if the information is used to lay out building lines and “B” if it is not.
Location of all utilities on plot
Information used to lay out building lines. Select “A” if the information is used to lay out building lines and “B” if it is not.
Location of benchmark and grade
Information used to lay out building lines. Select “A” if the information is used to lay out building lines and “B” if it is not.
Location and dimensions of easement(s)
Information used to lay out building lines. Select “A” if the information is used to lay out building lines and “B” if it is not.
Distance from utility pole to building
Information used to lay out building lines. Select “A” if the information is used to lay out building lines and “B” if it is not.
Dimensions (length and width) of building
Information used to lay out building lines. Select “A” if the information is used to lay out building lines and “B” if it is not.
Orientation of building on lot (square or diagonal)
Information used to lay out building lines. Select “A” if the information is used to lay out building lines and “B” if it is not.
Location of water supply
Information used to lay out building lines. Select “A” if the information is used to lay out building lines and “B” if it is not.
Dimensions of property
Information used to lay out building lines. Select “A” if the information is used to lay out building lines and “B” if it is not.
Setback from sidewalk
Batter boards provide a place to check that building lines for excavation and construction have been correctly placed.
Batter boards provide a place for stretching a line used to establish building lines for excavation and construction.
Determine common methods used to square building lines. Select “A” if the method is used to square building lines and “B” if it is not.
2-4-2 method
Determine common methods used to square building lines. Select “A” if the method is used to square building lines and “B” if it is not.
Horizontal method
Determine common methods used to square building lines. Select “A” if the method is used to square building lines and “B” if it is not.
Transit method
Determine common methods used to square building lines. Select “A” if the method is used to square building lines and “B” if it is not.
Laser method
Determine common methods used to square building lines. Select “A” if the method is used to square building lines and “B” if it is not.
3-4-5 method
Determine common methods used to square building lines. Select “A” if the method is used to square building lines and “B” if it is not.
Diagonal method
Information used to lay out building lines. Select “A” if the information is used to lay out building lines and “B” if it is not.
Dimensions (length and width) of building